Start by fixing battens to the building framework. Battens
will also need to be fixed around the periphery of any openings
e.g. a window.
Fixing starter trims
Before fixing the initial starter trim,
make a final inspection of the building substrate and
check if any special consideration needs to be taken into
account with regards to drainage and ventilation
Working from a line level, fix the starter
trim to the lower timber batten.
Use 30mm clad pins
Fixing vertical trims
All vertical trims should be fixed to perimeter battens.
Fixing cladding top finish trim
Top trims and trims around windows should also be fixed
to perimeter battens.
Fixing internal/external corner trim
Note:
The same product works as both
an internal and external corner trim. Fix the back half
initially and clip the cover on after cladding has been
fitted